Council is thrilled to announce that the works reflecting the adopted Parking Design for Currie CBD are commencing next week (19 May 2025). The project is expected to be completed by 26 June 2025.

To minimise disruptions, the works will be delivered in five stages as outlined below:

Stage 1
• Construction of new kerb bulbing and access ramps on Meech Street, opposite Memorial Park and the Senior Citizens Club.

Stage 2

• Construction of a new access ramp opposite IGA Supermarket, connecting to the new shared DA space (Main Street).
• Construction of a new access ramp opposite IGA Supermarket and a pedestrian refuge island opposite the King Island Hotel car park (Main Street).

Stage 3
• Construction of new access ramps and kerb bulbing opposite Foodworks and King Island Providore (Main Street).

Stage 4
• Construction of a new access ramp for the Disability Access (DA) space opposite the Westpac ATM on Edward Street.
• Construction of new access ramps and kerb bulbing opposite the Westpac Bank and diagonally opposite the Post Office (Main Street).
• Construction of a new access ramp opposite the Post Office, connecting to the new shared space (Main Street).

Stage 5
• Construction of new parking alignment on Edward Street, Main Street, and Meech Street, as shown in the adopted plans: Main St Parking Design Feb 24

There will be no road closures during the course of the project. However, as per the attached Traffic Management Plan, ‘Road Work Ahead – 40 km/h’ and End Road Work – 50 km/h signs will be placed at designated locations.

For Stages 1 to 4, a few parking spots will be temporarily closed to allow for safe and efficient construction. We will notify affected shops 2 days in advance as we progress through each stage.

During Stage 5, when we undertake the new parking alignment, we will divide the section into three areas to manage the work efficiently. Some major sections of parking will be closed for 1–2 days during this stage. We will aim to carry out these works in the late afternoons, where possible, to minimise business disruption.

Traffic Controllers will be in place, as needed, throughout the works and will help to guide drivers into safe and available parking.  For the safety of workers and the public, please adhere to all signage and follow all instructions given by work crews on site.

We appreciate your patience and assistance while we complete this exciting project.