2019 Road Sealing Program

Subject to weather and other operational constraints, the proposed resurfacing program is as follows:

Munros Road (Don Kendall Drive 4km towards Stricklands Road) Day 1Monday, 18 March 2019
Munros Road Day 2Tuesday, 19 March 2019
Munros Road Day 3Wednesday, 20 March 2019
Gatenby Car ParkThursday, 21 March 2019
AirportThursday, 21 March 2019
High School (Possibly defer to Saturday)Friday, 22 March 2019
Grassy Road (State Growth – 1.7 km – near Lancaster Road towards Robins Road)Monday, 25 March 2019
Grassy Road at Sea Elephant (State Growth)Tuesday, 26 March 2019
South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 1Tuesday, 26 March 2019
South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 2Thursday, 28 March 2019
South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 3Friday, 29 March 2019
Egg Lagoon Bridge ApproachesMonday, 1 April 2019
Charles StreetTuesday, 2 April 2019
Private works subject to agreementWednesday, 3 April 2019
Private works subject to agreementThursday, 4 April 2019