2019 Road Sealing Program
Subject to weather and other operational constraints, the proposed resurfacing program is as follows:
| Munros Road (Don Kendall Drive 4km towards Stricklands Road) Day 1 | Monday, 18 March 2019 |
| Munros Road Day 2 | Tuesday, 19 March 2019 |
| Munros Road Day 3 | Wednesday, 20 March 2019 |
| Gatenby Car Park | Thursday, 21 March 2019 |
| Airport | Thursday, 21 March 2019 |
| High School (Possibly defer to Saturday) | Friday, 22 March 2019 |
| Grassy Road (State Growth – 1.7 km – near Lancaster Road towards Robins Road) | Monday, 25 March 2019 |
| Grassy Road at Sea Elephant (State Growth) | Tuesday, 26 March 2019 |
| South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 1 | Tuesday, 26 March 2019 |
| South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 2 | Thursday, 28 March 2019 |
| South Road (2.5 km from Old Grassy Road towards Ettrick River) Day 3 | Friday, 29 March 2019 |
| Egg Lagoon Bridge Approaches | Monday, 1 April 2019 |
| Charles Street | Tuesday, 2 April 2019 |
| Private works subject to agreement | Wednesday, 3 April 2019 |
| Private works subject to agreement | Thursday, 4 April 2019 |